Green Leaf Medical Project
TEI Electrical Solutions completed a large project for Green Leaf Medical, a legalized medical marijuana growing facility. The scope of work was extensive and the time schedule was tight for the 41,000 square foot facility.
The scope of this project was for Phase 1 & 2, which includes 23,000 square feet of growing rooms and office space. The building previously served as a printing plant, so the power systems had to be upgraded to accommodate the new use. This included installation of a new 4,000 amp electrical service and a Square D Powerlink power distribution system. These systems are designed to control the lighting and the Argus environmental equipment, which maintains consistent temperature and humidity, vital to the stages of growth for these plants.
TEI Electrical Solutions worked collaboratively with Morgan-Keller Construction Company to install over 900 light fixtures and 450 special grow lights. A 550 KW diesel generator and 1,000 gallon fuel tank were also installed to supply backup power which is critical to the success of the Green Leaf business. Connections were also provided for multiple HVAC split systems, roof top units, interior handling equipment, fire alarm systems, and communication raceways.
The project was completed in just seven months, thanks to TEI Electrical Solutions proficiency for prefabrication and the use of the Trimble Optical and Laser Construction layout tools. These innovative capabilities were major factors in keeping the project on time, and in line with specifications.
See some other work that TEI has completed!
About TEI: TEI provides quality workmanship in all aspects of new construction and renovation projects for both public and private sector clients. With knowledgeable and seasoned in-house construction professionals, TEI is experienced in a broad variety of facility types, including data centers, research laboratories, healthcare facilities, secure buildings, office and administrative, educational and industrial.